Traffic Advisory
Starting Monday, October 30*, the City will have a contractor begin the grind/inlay and overlay project on several streets. Affected homes and businesses will be notified by the placement of ‘No Parking’ signage at least 24 hours in advance by the contactor.
*Work dates are subject to weather and could change. Please stay tuned for updates on the project schedule.
What is a grind/inlay?
- Grind/inlay involves grinding areas of pavement failure to a depth of 2-3” and pouring new asphalt in place. The new asphalt must be compacted and allowed to cool prior to letting traffic on it.
Our goal is to minimize any inconvenience this work might cause. Thank you for your patience as we complete this important pavement management project.
| Grind/Inlay Project | ||
|---|---|---|
| 6th Street (South of railroad), 18th (E St to G St), 15th Street (I St to K St) | Monday, October 30 | |
| 20th Street (C St to I St) and G Street (20th St to Washougal River Rd) | Tuesday, October 31 | |
| Cancelled Due to Weather | ||
| Cancelled Due to Weather | ||
| Grind/Inlay 34th Street (Evergreen to Gause), Grind Steamboat Landing | Friday, November 3 | |
| Grind/Inlay Q Street (32nd St – 33rd St), G Street (Washougal River Rd to 20th St), and pave Steamboat Landing | Monday, November 6 | |
| Cancelled Due to Weather | ||
| Pave Steamboat Landing, Grind/Inlay 21st Street (Main St. to dead end north of C St), and 23rd Street (E St – G St) | Wednesday, November 8 | |
| Grind/Inlay 18th Street (E St – G St), G Street (Washougal River Rd – 20th St), and I Street (west of 20th St) | Thursday, November 9 | |
| Grind/Inlay Q Street (32nd St – 33rd St), and S & T Circle (off of 39th St) | Friday, November 10 | |
| Grind/Inlay Q Street (32nd St – 33rd St), and S & T Circle (off of 39th St) | Wednesday, November 15 | |
| *Work dates are subject to weather and could change. |